Installation Steps of Offshore Conductors by Jetting Method

#### 1. Preinstallation Preparations

– **Assemble the conductors**: Attach a jetting head to the bottom and connect a swivel joint to the top.

– **Commission the mud pump**: Prepare highviscosity drilling fluid.

– **Position the platform**: Use Differential Global Positioning System (DGPS) for platform positioning and survey the seabed soil (which should be soft sandy soil).

#### 2. Lowering and Jetting to Penetrate the Seabed

– **Lower the conductor**: Lower the conductor above the mud surface and align it with a laser (allowable deviation ≤ 5cm).

– **Initiate the operation**: Start the mud pump (highvelocity jet flow) and the rotary table (lowspeed rotation) to erode the soil. The conductor sinks under its own weight at a speed of 0.5 – 1m/min.

– **Survey the inclination**: Measure the inclination every 5 – 10m of lowering (verticality ≤ 1°/30m). If the limit is exceeded, adjust the direction slightly.

#### 3. Fixing and Followup

– **Stop the pump**: Once the designed depth is reached, stop the mud pump and let it stand for 2 – 4 hours to allow the soil to settle.

– **Fix and seal**: Fix the platform with a conductor head at the top and inject lowstrength cement slurry into the annulus for sealing.

– **Connect and test**: Connect the blowout preventer. After a pressure test, proceed to the drilling operation.

### Core Advantages

This method features low cost and high speed, and is suitable for soft formations in shallow waters (water depth < 100m).

Leave a Comment

Your email address will not be published. Required fields are marked *

شريك Offshore Solutions Co., المحدودة. يسعى إلى أن يكون رائدًا عالميًا في الناهضين البحريين. نحن نؤيد مفهوم “التميز والموثوقية”, تهدف إلى مقابلة العملاء’ الاحتياجات وتعزيز صناعة الطاقة العالمية.

اشترك في رسالتنا

للاستفسارات حول منتجاتنا أو مقدمة, يرجى المغادرة لنا وسنكون على اتصال 24 ساعات.

اتصال

انتقل إلى الأعلى
اترك رسالتك